  • NGT asked for details on drainage and waste for Phase II of Yamuna cleaning
  • NGT expressed interest in monitoring the 2nd phase of the cleaning project
  • Under Phase II, a total of 14 sewage treatment plants are to be constructed

New Delhi: The National Green Tribunal directed the Delhi Jal Board (DJB) to state the total number of drains falling in the second phase of the Yamuna cleaning project and quality of waste being released into the river. A bench headed by NGT Chairperson Justice Swatanter Kumar asked the DJB and the National Mission for Clean Ganga (NMCG) to submit all the details by tomorrow. The green panel also sought information on the number of sewage treatment plants (STP) which are proposed to be constructed in Phase-II, which primarily deals with Shahdara, Barapullah and other drains.

Also Read: Centre To Bear 70% Cost For Yamuna Sewage Treatment: NGT

During the hearing, the tribunal noted that work on the Phase-I of the cleaning, christened as ‘Maily Se Nirmal Yamuna’ Revitalisation Project, was already in progress and it would now monitor the work of the next stage. The Phase-I of the clean Yamuna project aims to lower the pollution levels in the Najafgarh and Delhi Gate drains, while Phase-II deals with Shahdara, Barapullah and other drains.

The NGT had classified the entire issue of cleaning the river into different broad heads — matters related to finance, sites for setting up of STPs, future implementation of projects and proposed action with regard to Phase-II of the Yamuna cleaning project.

Also Read: Delhi’s Lt. Governor Anil Baijal Appreciates Centre’s Sewage Treatment Project At Sarai Kale Khan

The tribunal was earlier informed that a total of 14 STP projects were to be constructed to clean waste water. Of these, seven are to be built by the DJB from its own funds. The green panel had said that pollution in the Yamuna was of serious concern as it was highly contaminated by industrial effluents and sewage.

It had noted that almost 67 per cent of the pollutants reaching Yamuna would be treated by the two sewage treatment plants at Delhi Gate and Najafgarh under the first phase of the ‘Maili se Nirmal Yamuna Revitalisation Project’.

Also Read: River Activists Bat For Revival And Rejuvenation Of Yamuna To Save The Taj Mahal