Centre To Bear 70% Cost For Yamuna Sewage Treatment: NGT

Currently only active on papers, the “Maily Se Nirmal Yamuna” plan aims at treating the sewage and waste water reaching Yamuna through drains, the National Green Tribunal said

Yamuna pollution
Highlights
  • Yamuna river revival project has been delayed by over 8 months
  • First phase was supposed to have been completed by March 31, 2017
  • 14 STPs are to be made at Najafgarh drain and Delhi Gate in phase 1

New Delhi: The National Green Tribunal (NGT) has directed the Central government to bear 70 percent of the cost for constructing 14 Sewage Treatment Plants (STPs) under the first phase of the Yamuna river revival project which has been delayed by over eight months due to lack of cooperation among agencies and a fund crunch. The bench, headed by NGT Chief Justice Swatanter Kumar, also directed the Delhi Jal Board (DJB) to bear the remaining 30 percent of the cost.

Also Read: Delhi’s Lt. Governor Anil Baijal Appreciates Centre’s Sewage Treatment Project At Sarai Kale Khan

For sewage management in Yamuna at Delhi, Central government and DJB will share 70-30 per cent of the cost. If the cost exceeds 30 percent, then the Delhi government will provide financial assistance to the DJB, Justice Kumar said.

Currently only active on papers, the “Maily Se Nirmal Yamuna” plan aims at treating the sewage and waste water reaching Yamuna through drains. Under the first phase, supposed to have been completed by March 31 this year, 14 STPs are to be made at Najafgarh drain and Delhi Gate – the most polluting.

Also Read: Chief Minister Arvind Kejriwal Approves 7 Sewage Treatment Plants in North Delhi

More STPs are to be constructed at other drains along the Yamuna under Phase-II that will include drains along Shahdara, Barapullah and others. The DJB had earlier said that it will construct seven out of 14 STPs, and expected the National Mission for Clean Ganga (NMCG) to extend financial support – the major cause of delay.

At present, DJB has started working on five STPs while a survey is being done for the other two. The estimation of Phase-I of the project, under which 14 STPs are to be built, is still unclear.

The tribunal, in a January 2015 judgment, ordered to deal with all components of controlling and preventing pollution in the Yamuna. The green panel had noticed that almost 67 percent of the pollutants reaching the Yamuna would be treated by the two sewage treatment plants at Delhi Gate and Najafgarh in Phase-I.

Also Read: National Green Tribunal Slaps Heavy Fines On Delhi’s Mass Waste Generators For Failing To Manage And Treat Sewage

The Yamuna traverses a distance of about 46 km along Delhi. According to the Central Pollution Control Board, while the river’s stretch between Wazirabad barrage to downstream Okhla barrage is less than two per cent of the entire river stretch, it receives around 70 per cent of the total pollution load there.

Highlights: Banega Swasth India Launches Season 10

Reckitt’s Commitment To A Better Future

India’s Unsung Heroes

Women’s Health

हिंदी में पढ़ें

This website follows the DNPA Code of Ethics

© Copyright NDTV Convergence Limited 2024. All rights reserved.